Thursday, May 21, 2015

ONE YEAR & ONE DAY LATER- THE BIG POUR

366 days ago the first shovelfuls of earth were moved on the Lovango lot.  Today, the final yard of concrete was poured for the cottage.  It's been a long and winding road that has nonetheless been productive and always forward moving.  As good as we could have hoped for given the challenges.

The logistics of this pour were staggering, beginning with the forms themselves and the enormous 12' back wall.  That it all came together as beautifully as it did is a real testament to Dan and his crew.  Exceptional work.

Things should be simpler (not easy) as we come out of the dirt.  In the next couple of weeks the forms will be stripped and earth will be back-filled and finish graded.  All the structural lumber has been ordered and should be shipping from Florida in the next few weeks and arriving to a site that will be ready to emerge from its new, solid foundation.

The morning dawned clear and calm, a perfect day for landing on Lovango.  The barge made two runs with 3 full trucks on each.  The pumper truck was delivered the day before and returned on the second run.


Filling the footers first.  Note stainless steel anchor bolts positioned pre-pour.


Waiting for the second barge run.  This is where things stood after the first three truckloads of concrete.
All poured, barge and trucks back in St. Thomas.  Beginning the spin cycle as evening arrived.



'nuf said.

Tuesday, May 19, 2015

BIG DAY TOMORROW

Dan has been working on his captain's license the last couple of weeks but has everything set up for the final pour tomorrow morning.  Should get the footers, floor, cistern cap, and 12' back wall in one felled swoop.  The pumper truck is on the beach and ready to go.  Dan is looking to pour 54 yds (6 truckloads) in two barge runs.  Last time he went with two trucks per run... this time three in hopes of speeding things up.  Big day tomorrow.  Fingers crossed.

Pumper truck delivered to the beach today all ready for pumping 54 yds of concrete up to the site.  


Monday, May 4, 2015

STILL STILL PREPPING FOR SLAB

... but getting really close!  Alot of work forming the 12' back wall and laying in both the reinforcing steel and plumbing that will run through floor and back wall.  And building the scaffolding that will facilitate the pour.
Pano shot from the cistern looking to the 12' back wall.  Mechanical room (batteries and pump) back left, laundry room center, and storage back right.  Lots of rebar!  The shed in the background is on Dan's property and the cottage to the right is Capt Phil's.

The back wall is being laid back 1.5" over the 12' height to try to balance pressures from the bank.

Looking down on the floor.  The dug out spot is a footing to support a carrying post.

Impressive array of scaffolding to provide access for folks to handle the concrete.

Shot from the top of the driveway.  St Thomas in the back ground.

Monday, April 20, 2015

ON SITE VISIT

Sailing vacation down in the US/BVI gave us the chance to stop by the site and review things with both Dan (contractor/neighbor) and Heidi (architect).  A few tweaks were made in a plan that seems to (finally) be settling.  Progress on forms for slab and back wall are slow but steady.  Dan is hoping to have the complete structure framed and closed up by the time he goes on vacation for  month or more beginning July 21.  I write this down to have a reference.

Welcoming Committee chair and co-chair Olive Oyl (Great Dane) and Eeyore (Bassette Hound) hold fort in the beach shack.
Forms for 12' concrete wall with rebar and plumbing almost all installed.  Front forms are next and then ready to pour.  Block out on back wall is for door outside from upstairs bathroom to outdoor shower.  Washer hook-up is below that.


Family reviews prints with Dan and Heidi.


Plan has kitchen/living/dining/bath/master bedroom downstairs and three small bedrooms and a bath upstairs.  Both showers are connected to bathrooms but outside to save space and take advantage of the climate.

Tuesday, April 7, 2015

STILL PREPPING FOR SLAB

Debating the height of the back wall (to be poured).  Growing the footprint 6 feet in the back has put us deeper into the bank (and closer to it) and what was going to work as an 8' back wall before is likely going to wind up at 12'.  Also looking at "battering" the wall- leaning it into the bank about 1.5" to try to balance the pressure of the bank.  Fortunately the earth is relatively stable there, sort of a shale-like ledge that can be broken but not prone to shifting.

While soils are stable, plans are not.  The change in size and shape of the footprint have caused much last minute adjustments and it appears we are almost completely abandoning the original plans for something that better fits the added space.  First floor is now the main living area and plumbing drains have been laid in... written in stone, as they say.  Second floor is still tbd.


2 tons of rebar coming over from St Thomas.
2 tons of rebar getting humped up the hill to site on Dan's Toyota truck.


Laying in the drains.
No more changes to drains.


Sunday, March 22, 2015

PREPPING FOR A SLAB

Another week n the dirt... forming up to pour the slab and cistern cap.  We'll also be pouring a back wall.  Initially this was going to be but out of blocks on top of the slab but the success Dan had with the cistern pour has encouraged us to try the faster and more rugged option.  We have also grown the footprint from 24' deep to 30'.  The initial excavation created plenty of space and Dan was looking for more room for mechanicals- batteries, pumps, etc..  Growing the footprint seemed pretty straightforward and cost effective.  We are playing with different floor plans to best take advantage of the change.

Dan is also working with DPNR regarding best barge landing location.

Cistern capped and ready to pour.  There will be a 4" step down from the main building on to the porch (top of the cistern).

40' wide and 30' deep main cottage area will be built on a slab.
Trying to determine the height of the back (poured) wall.  8', 10', and 12' heights for reference.
We've created a flat lawn area to the east of the footpint.



Monday, March 9, 2015

BACK TO DIRT MOVING

The trac hoe arrived back on Lovango this morning to backfill the cistern and begin grading for the slab.  Dan also brought over the aerobic septic system that will be laid in place, as well.
The trac hoe and Dan's truck (R) loaded with the septic system arrive on Lovango this morning.
Trac hoe moving into position.
The cistern backfilled.