Sunday, March 20, 2016

UNDER PRESSURE

The cistern is 3/4 full (16,000+ gallons) and the rough plumbing is completed and pressurized.  A couple of toilets are on site awaiting bathroom floor tile and final hook-up to the aerobic septic system.  Consolidation of stateside goods for the container is on schedule, as well.  Still looking good for flushing and running water and a boat-load of Ikea furniture on site by April 19.
40 lbs of pressure in the line.
The picture of organization- pump and tank and lines in the mechanical room.
The battery farm.  12 cells.
First look at tile laid down in the downstairs bedroom.  Grout to follow.
First look at dock repairs (from Hurricane Erica damage) ... still some work on decking but frame is fresh and squared up.